Judul ArtikelAnalisis Setting dan Koordinasi Overcurrent Relay (OCR) dan Ground
Fault Relay (GFR) pada Penyulang Garut Kota (GAKO) 20 kV di Gardu
Induk Garut PT. PLN (Persero) UP2D Jawa Barat
Abstrak (Bhs. Indonesia)Keandalan sistem distribusi tenaga listrik sangat bergantung pada kinerja
sistem proteksi dalam mendeteksi dan mengisolasi gangguan secara selektif. Pada
jaringan distribusi 20 kV, Overcurrent Relay (OCR) dan Ground Fault Relay
(GFR) berperan penting, sehingga diperlukan analisis setting dan koordinasi
proteksi berbasis perhitungan dan simulasi.
Penelitian ini menganalisis setting dan koordinasi OCR dan GFR pada
Penyulang Garut Kota (GAKO) 20 kV di Gardu Induk Garut PT PLN (Persero)
UP2D Jawa Barat menggunakan data aktual jaringan, perhitungan arus hubung
singkat, dan simulasi dengan ETAP 21.0.1. Analisis dilakukan pada sisi incoming,
outgoing, Zona 1, dan Zona 2 dengan mengacu pada karakteristik IEC Standard
Inverse. Hasil simulasi menunjukkan bahwa sistem proteksi telah bekerja selektif
dan berjenjang, dengan beda waktu tunda antar relay OCR dan GFR sekitar ±0,3
detik, sesuai standar IEC. Meskipun demikian, terdapat perbedaan antara setting
relay eksisting dan hasil simulasi pada beberapa zona, yang menunjukkan
perlunya optimasi dan evaluasi setting secara berkala agar sistem proteksi
semakin andal.

Abtrak (Bhs. Inggris)The reliability of an electrical distribution system strongly depends on
the performance of its protection system in detecting and isolating faults
selectively. In 20 kV distribution networks, Overcurrent Relay (OCR) and Ground
Fault Relay (GFR) play a crucial role; therefore, an analysis of relay setting and
coordination based on numerical calculation and system simulation is required.
This study analyzes the setting and coordination of OCR and GFR on the
Garut Kota (GAKO) 20 kV feeder at Garut Substation, PT PLN (Persero) UP2D
West Java, using actual network data, short-circuit current calculations, and
simulations performed with ETAP 21.0.1. The analysis covers the incoming,
outgoing, Zone 1, and Zone 2 sections, referring to the IEC Standard Inverse
characteristic. Simulation results indicate that the protection system operates
selectively and in a coordinated manner, with time delay differences between OCR
and GFR relays of approximately ±0.3 seconds, which complies with IEC
standards. However, differences between existing relay settings and simulation
results were identified in several zones, indicating the need for periodic
optimization and evaluation of relay settings to further enhance protection system
reliability.
Keywords : protection system, Overcurrent Relay, Ground Fault Relay, protection
coordination,
Kata kunciKata kunci : sistem proteksi, Overcurrent Relay, Ground Fault Relay, koordinasi proteksi, hubung singkat
Pembimbing 1Prof. Dr. Eng Suroso S.T., M.Eng., IPU
Pembimbing 2Ir. Winasis S.T., M.Eng