| Judul Artikel | PENERAPAN METODE CROSS ENTROPY PADA PENJADWALAN HYBRID FLOWSHOP UNTUK MEMINIMASI MAKESPAN (STUDI KASUS DI PT. XYZ) |
| Abstrak (Bhs. Indonesia) | PT. XYZ di mana mereka memproduksi lima jenis plywood berdasarkan ketebalannya dengan melewati proses yang sama di setiap stasiun kerja kecuali operator di stasiun kerja rotary tetap memilih panel untuk menyesuaikan ketebalan komposisi veneer yang membentuk lapisan plywood. PT. XYZ memiliki kebijakan produksi yaitu menerapkan sistem MTO (make to order) dan FCFS (first come, first served) sebagai prioritas pengerjaannya. Perusahaan sering mendapat komplain dari customer karena waktu penyelesaian pesanan yang lama. Oleh karena itu diperlukan perbaikan penjadwalan yang dapat mengurangi waktu penyelesaian produksi atau meminimasi makespan. Aliran proses produksi pada perusahaan saat ini menggunakan Hybrid Flow Shop (HFS). Metode yang digunakan dalam penelitian ini adalah Metode Cross Entropy (CE) karena unggul dalam menangani masalah kombinatorial, termasuk penjadwalan. Sebagai prosedur adaptive importance sampling, metode ini dikenal memiliki reputasi yang baik saat diterapkan pada berbagai masalah kompleks. Hasil dari penelitian ini merupakan urutan job usulan yang dihasilkan metode cross entropy adalah job 7 – 9 – 8 – 6 – 5 – 3 – 2 – 1 – 4 dengan nilai makespan sebesar 15.559 menit, sedangkan pada penjadwalan awal adalah 15.816 menit, perbedaan makespan urutan job usulan dan awal sebesar 257 menit atau 1,62 %. |
| Abtrak (Bhs. Inggris) | PT. XYZ manufactures five types of plywood based on thickness, following the same process at each workstation, except at the rotary workstation where operators select panels to adjust the veneer composition thickness forming the plywood layers. PT. XYZ implements a production policy of Make to Order (MTO) and First Come, First Served (FCFS) as their prioritization strategy. The company often receives complaints from customers due to long order completion times. Therefore, an improvement in scheduling is needed to reduce production completion time or minimize makespan. The current production process flow in the company uses a Hybrid Flow Shop (HFS) system. The method used in this research is the Cross Entropy (CE) method, which excels in handling combinatorial problems, including scheduling. As an adaptive importance sampling procedure, this method is known for its good reputation when applied to various complex problems. The results of this research show the job sequence generated by the cross entropy method is job 7 – 9 – 8 – 6 – 5 – 3 – 2 – 1 – 4 with a makespan value of 15,559 minutes, whereas the initial schedule was 15,816 minutes. The difference in makespan between the proposed and initial job sequences is 257 minutes or 1.62%. |
| Kata kunci | Cross Entropy, Makespan, Hybrid Flow Shop, Plywood. |
| Pembimbing 1 | Dr.Ing. Sugeng Waluyo, S.T., M.Sc. |
| Pembimbing 2 | Ir.Katon Muhammad, S.T., M.T. |
| Pembimbing 3 | |
| Tahun | 2024 |
| Jumlah Halaman | 8 |
| Tgl. Entri | 2024-08-26 15:30:35.622392 |