| Judul Artikel | PENJADWALAN FLOWSHOP UNTUK MEMINIMASI TOTAL TARDINESS COST DAN TOTAL OVERTIME COST PADA PRODUKSI REINFORCEMENT BAR DAN FOOTPLATE MENGGUNAKAN METODE MIXED INTEGER PROGRAMING (STUDI KASUS: UD BAGUS NANANG JAYA) |
| Abstrak (Bhs. Indonesia) | UD Bagus Nanang Jaya (BNJ) merupakan perusahaan manufaktur dalam bidang bahan konstruksi yang memproduksi reinforcement bar dan footplate. Terdapat 4 produk yang dikerjakan pada 3 stage dalam model produksi flowshop. Saat ini BNJ menjadwalkan produksinya bedasarkan prinsip first come first served dan belum memiliki penjadwalan pasti. Model penjadwalan saat ini mengakibatkan adanya keterlambatan produksi serta menghasilkan tardiness cost dan overtime cost yang harus dikeluarkan. Oleh karena itu, penelitian ini bertujuan melakukan penjadwalan dengan kriteria performansi berupa minimasi total tardiness cost dan total overtime cost. Pada penelitian ini, permasalahan penjadwalan diselesaikan menggunakan mixed integer programming (MIP) dengan fungsi tujuan berupa minimasi total tardiness cost dan total overtime cost. Berdasarkan penjadwalan yang telah dibangun menggunakan MIP, hasil menunjukkan bahwa terdapat penurunan tardiness cost dari Rp. 432.588,00 menjadi Rp. 0,00 atau sebesar 100% dari penjadwalan awal. Penurunan juga terjadi pada overtime cost dimana berkurang dari Rp. 488.666,00 menjadi Rp. 436.267,00 atau 10.72% dari penjadwalan awal. Pengujian model dilakukan untuk mengetahui perubahan hasil penjadwalan berdasarkan perubahan parameter. Hasil simulasi menunjukkan adanya persamaaan nilai tardiness cost yang dihasilkan sedangkan overtime cost berubah. Hal tersebut menunjukkan bahwa perubahan jumlah job dan jumlah unit yang diproduksi tidak mempengaruhi nilai tardiness cost namun berpengaruh pada nilai overtime cost. Kemudian berdasarkan penjelasan tersebut dapat disimpulkan bahwa model yang dibangun mampu menyelesaikan permasalahan keterlambatan yang dialami perusahaan dan menghasilkan penjadwalan yang lebih baik dari penjadwalan awal. |
| Abtrak (Bhs. Inggris) | UD Bagus Nanang Jaya (BNJ) is a manufacturing company in the field of construction materials that produces reinforcement bars and footplates. There are 4 products that are worked on at 3 stages in the flowshop production model. Currently, BNJ schedules its production based on the principle of first come first served and does not yet have a definite schedule. The current scheduling model results in tardy jobs and results in tardiness costs and overtime costs that must be incurred. Therefore, this research aims to carry out scheduling with performance criteria in the form of minimizing total tardiness costs and total overtime costs. In this research, the scheduling problem is solved using mixed integer programming (MIP) with the objective function of minimizing total tardiness costs and total overtime costs. Based on the scheduling that has been built using MIP, the results show that there is a reduction in tardiness costs from IDR 432,588.00 to IDR 0.00 or 100% of the initial scheduling. A decrease also occurred in overtime costs which were reduced from IDR 488,666.00 to IDR 436,267.00 or 10.72% from the initial scheduling. Model testing is carried out to determine changes in scheduling results based on parameter changes. The simulation results show that there is a similarity in the resulting tardiness cost value while the overtime cost changes. This shows that changes in the number of jobs and the number of units produced do not affect the tardiness cost value but do affect the overtime cost value. Then, based on this explanation, it can be concluded that the model built is able to solve the delay problems experienced by the company and produce better scheduling than the initial scheduling. |
| Kata kunci | tardiness cost, overtime cost, multi due date, flowshop scheduling, mixed integer programming. |
| Pembimbing 1 | Ir. Ayu Anggraeni Sibarani, S.T., M.T. |
| Pembimbing 2 | Ir. Hasyim Asyari, S.T., M.Sc. |
| Pembimbing 3 | |
| Tahun | 2023 |
| Jumlah Halaman | 128 |
| Tgl. Entri | 2023-11-24 14:44:30.780052 |
|---|