Judul ArtikelKAJIAN PERENCANAAN KEBUTUHAN DAN PENYEDIAAN ENERGI LISTRIK PADA PLTA MRICA, DI KABUPATEN BANJARNEGARA MENGGUNAKAN APLIKASI LEAP
Abstrak (Bhs. Indonesia)Kabupaten Banjarnegara telah melaksanakan otonomi daerah, Potensi pengembangan daerah yang terdapat di Kabupaten ini meliputi sektor rumah tangga, bisnis, industri, pariwisata dan pemerintah. Banjarnegara merupakan kabupaten dengan UMK terendah di Provinsi Jawa Tengah. Waduk Mrica dikenal dengan waduk PLTA Panglima Besar Soedirman terletak di Kecamatan Bawang, Kabupaten Banjarnegara, Provinsi Jawa Tengah. Tujuan utama dibangunnya waduk Mrica adalah untuk PLTA dengan kapasitas terpasang 180,93 MW. Penelitian ini bertujuan mengetahui pertumbuhan konsumen dan pertumbuhan kebutuhan energi listrik di Kabupaten Banjarnegara serta merencanakan produksi listrik di PLTA waduk Mrica.
Perencanaan ketenagalistrikan di Kabupaten Banjarnegara dilakukan untuk mengantisipasi krisis energi. Perhitungan prakiraan energi dilakukan berdasarkan pola penggunaan energi yang sama seperti yang terjadi pada tahun dasar dan juga memperhatikan faktor perekonomian di Kabupaten Banjarnegara. Selanjutnya dilakukan simulasi menggunakan aplikasi LEAP (Low Emissions Analysis Platform) untuk meramalkan permintaan energi listrik di kabupaten Banjarnegara dan penyediaan energi listrik oleh PLTA Mrica dengan skenario Business as Usual (BAU). Dalam melakukan skenario digunakan pendekatan trend dan ekonometri.
Hasil proyeksi menunjukan rata-rata pertumbuhan konsumsi energi listrik total Kabupaten Banjarnegara dari tahun 2019-2031 (12 tahun) adalah sebesar 4,5 % per tahun. Proyeksi jumlah pelanggan energi listrik Kabupaten Banjarnegara menunjukkan peningkatan dari tahun 2019-2031 yaitu sebesar 3,13% per tahun. Hasil visualisasi transformasi dan distribusi kebutuhan energi PLTA Mrica Banjarnegara dalam 12 tahun mengalami kenaikan permintaan energi listrik sebesar 54,4% dan produksi PLTA waduk Mrica juga mengalami kenaikan sebesar 22,6%. Dari hasil produksi dengan menggunakan 3 generator utama menunjukan bahwa PLTA waduk Mrica mampu menyuplai listrik di Kabupaten Banjarnegara sampai tahun 2031.
Abtrak (Bhs. Inggris)Banjarnegara Regency has implemented regional autonomy. The potential for regional development in this Regency includes the household, business, industry, tourism and government sectors. Banjarnegara is a district with the lowest UMK in Central Java Province. The Mrica Reservoir is known as the Panglima Besar Soedirman Hydropower Reservoir located in Bawang District, Banjarnegara Regency, Central Java Province. The main purpose of building the Mrica reservoir is for a hydropower plant with an installed capacity of 180.93 MW. This study aims to determine the growth of consumers and the growth of electricity demand in Banjarnegara Regency and to plan electricity production in the Mrica Dam hydropower plant.
Electricity planning in Banjarnegara Regency is carried out to anticipate the energy crisis. Calculation of energy forecasts is carried out based on the same pattern of energy use as occurred in the base year and also takes into account economic factors in Banjarnegara Regency. Furthermore, a simulation was carried out using the LEAP (Low Emissions Analysis Platform) application to forecast the demand for electrical energy in the Banjarnegara district and the supply of electricity by the Mrica hydropower plant with a Business as Usual (BAU) scenario.approaches are used trend and econometric
The projection results show that the average growth in total electricity consumption for Banjarnegara Regency from 2019-2031 (12 years) is 4.5% per year. The projected number of electricity customers for Banjarnegara Regency shows an increase from 2019-2031, namely 3.13% per year. The results of the visualization of the transformation and distribution of energy needs for the Mrica Banjarnegara hydropower plant in 12 years experienced an increase in demand for electrical energy by 54.4% and the production of the Mrica Reservoir hydropower plant also increased by 22.6%. From the production results using 3 main generators, it shows that the Mrica dam hydropower plant is able to supply electricity in Banjarnegara Regency until 2031.
Kata kunciEnergi, LEAP, PLTA Mrica, Banjarnegara
Pembimbing 1Ropiudin, S.TP., M.Si.
Pembimbing 2Priswanto, S.T., M.Eng.
Pembimbing 3
Tahun2022
Jumlah Halaman12
Tgl. Entri2022-11-22 14:00:33.574656
Cetak Bukti Unggah
© Universitas Jenderal Soedirman 2026 All rights reserved.