Judul ArtikelANALISIS SEDIMEN LAYANG ( SUSPENDED LOAD ) PADA BANGUNAN KANTONG LUMPUR BENDUNG SLINGA KABUPATEN PURBALINGGA
Abstrak (Bhs. Indonesia)Bendung Tetap Slinga sebagai bangunan pengatur muka air memiliki beberapa bangunan pelengkap salah satunya adalah bangunan kantong lumpur. Kantong lumpur merupakan salah satu bangunan pelengkap bendung yang berfungsi mengendapkan sedimen layang / suspended load yang melewati pintu intake. Besarnya angkutan sedimen layang dipengaruhi oleh beberapa hal seperti tingginya curah hujan, keberhasilan konservasi lahan. Pada penelitian ini peneliti mencoba untuk menganalisis tentang angkutan sedimen yang terjadi di kantong lumpur Bendung Slinga baik itu mengenai jumlah angkutan sedimen ataupun periode penggelontoran untuk menjaga keefektifan kantong lumpur.
Untuk mengetahui dan memperkirakan jumlah angkutan sedimen layang yang terjadi di kantong lumpur, pada penelitian ini menggunakan metode seksi hidrometri. Besarnya angkutan sedimen layang dihitung dengan beberapa parameter, yaitu kosentrasi, debit air dan gambar teknis bangunan itu sendiri.
Dari hasil perhitungan didapatkan nilai kosentrasi yang berbeda antara titik pengamatan sebelum di kantong lumpur dan setelah kantong lumpur. Debit sedimen layang yang diendapkan berdasarkan metode seksi hidrometri sebesar 84,129 ton/hari dan memiliki nilai efisiensi sebesar 38,862 % dengan metode selisih dan 6% dengan metode grafik. Dengan volume yang diendapkan sebesar 31,746 m3/hari dan volume efektif kantong lumpur bendung gerak serayu sebesar 698,448 m3, maka diperlukan periode penggelontoran sedimen yang mengendap selama 22 hari sekali.
Abtrak (Bhs. Inggris)Slinga weir as water level control structure has some complementary structures, one of the complementary structure is settling basin. Settling basin is one of the complementary structure that deposite suspended load passes through the intake gate. The amount of suspended load transport is influenced by several things such as high rainfall, the successfull of land conservation. This study, is analysing sediment transport that occurs in settling basin of Slinga weir both the amount of sediment transport and the flushing period to maintain the effectiveness of settling basin.
The hydrometric section was used to find and estimate the amount of suspended sediment transport that occurs in settling basin, to determine the amount of sediment transport in the settling basin there are several parameters that must be known i.e concentration, discharge flow and as built drawing of the building it self
Based on the calculation results it is obtained that concentration values are different between the two observation points before and after the settling basin. The suspended sedimentation transport based on the hydrometric section method is 84,129 tonnes / day and having a 38,862% efficiency rate with difference method and 6% efficiency rate with graphic method. With the volume deposited at 31,746 m 3 / day and the effective volume of settling basin Slinga weir of 698,448 m 3, the required period of flushing sediment that settles for 22 days.
Kata kunciBendung Slinga, Kantong Lumpur, Sedimen Layang.
Pembimbing 1Sanidhya Nika Purnomo, S.T.,M.T
Pembimbing 2Nastain, S.T,.M.T
Pembimbing 3
Tahun2016
Jumlah Halaman12
Tgl. Entri2016-11-14 16:06:38.073054
Cetak Bukti Unggah
© Universitas Jenderal Soedirman 2026 All rights reserved.